Båthamnsvägen Åkersberga
The Roslagsbanan expansion project aims to upgrade and extend the railway network with more tracks to improve its capacity, accessibility, and safety for commuters. At Åkersberga station, a comprehensive expansion has been completed, which includes new railway bridges and roads.
Client
AB Stockholm Lokaltrafik
Project type
Construction, Railway
Time frame
2017 - 2020
Contract
Design and Build Contract
Location
Stockholm
Roll
Production Manager for Main Contractor
Value
SEK 280 million
Roll
In this project, Pavel Seda served as production manager for Implenia Sverige AB, the project's main contractor.

Extensive reconstruction of Roslagsbana
Between 2017 and 2020, an extensive reconstruction of the Roslagsbanan at Båthamsvägen in Åkersberga was carried out, which included replacement of the level crossing with two new railway bridges and construction of new streets and roads. The work included complicated foundation work, and BEST-K operations was carried out during ongoing traffic on the tracks.
Scope of the project:
- Concrete construction of two bridges and a trough: complex foundation work with concrete piles on old lakebed
- BEST-K work on 1200-meter-long double track
- Drainage system with built-in pump station, stormwater reservoir
- District heating pipe, signal cables, electricity cables, road lighting
- Wall construction including paving, roundabout, parking areas
Effective management and innovative solutions
Pavel's role as Production Manager involved leading, coordinating, and control production, as well as assisting the design manager in adapting the design for the best possible execution and production methods. Special solutions, such as reinforced earth walls and temporary track embankments, where innovative solutions were implemented, were highlights of the project.
Challenging foundations during operation
In this project, the main focus was on coordination and time planing, as it involved many different stakeholders and needed to be adapted to the train traffic timetable. Most of the project was carried out with the trains in traffic, which made safety coordination a top priority. Among other things, a complex foundation of concrete and steel piles was installed while one of the double tracks was still in use. A strategic and systematic approach to the working environment led to the contractor receiving SL's award for the safest contractor of the year.
Do you want to know more?

Explore similar projects
Agicon has been entrusted with leading an exciting new railway project in Gerstaberg – a central part of the new high-speed railway, Ostlänken.
Agicon and Z-Rail are helping Sandahls in realizing an exciting railway project. The railyard is being upgraded to increase capacity and reduce maintenance costs.