Road 261 Ekerövägen E1

A new innovative bridge featuring a rotating steel section, along with an upgraded road between Ekerö and Lindö, has now been completed. In addition to improving connections between the municipalities, the project facilitates smoother passage for boat traffic. Commissioned by Trafikverket, Agicon has served as the lead consultant for Comsa in executing the project.

Client

Trafikverket

Project type

Construction, Bridge, Road

Customer

Comsa Sweden AB

Contract

Design and Build Contract

Time frame

2019 - 2024

Roll

Site Manager, Chief Surveyor, Surveying Technician

Scope

2 km Road and Movable Bridge

Value

SEK 340 million

Cooperation

The project is a design-build contract in collaboration with Trafikverket and Comsa AB, following ABT 06. Agicon has played a leading role in production management, surveying, and project coordination.

New swing bridge replaces old bascule bridge

The old bascule bridge in Ekerö was in great need of maintenance, with outdated machinery and only two lanes restricting traffic flow. As part of the Stockholm Bypass project, the new Tappströms Bridge has now been installed. This new swing bridge is more cost-effective to build, operate, and maintain. Additionally, Ekerövägen has become widened to include four lanes, a pedestrian and bicycle path, and the existing roundabout has been relocated. The new bridge features a rotating steel section that opens for boat traffic by lifting and then rotating the bridge.

Challenging groundworks

The work involved challenging ground conditions that placed significant demands on the complex foundation work for the bridge. To create a stable base for the bridge supports, temporary pile platforms were anchored into the bedrock, and retaining walls were driven into the ground. This method allowed for the removal of clay and silt, and seals were cast on top of the steel and concrete piles anchored in the bedrock. With the substructure in place, water was pumped out, and we were able to cast the bridge piers before the ground was then restored.

The bridge is pushed into place

The movable part of the bridge was delivered in fifteen steel sections and assembled on site. Using SPMTs and sliding jacks, the new bridge was pushed into place and lowered to its final position.


Do you want to know more?

Nebojsa Cadjenovic

Founder and surveying manager

Lazar Radojevic

Co-owner and surveying manager

Pavel Seda

Co-owner and project manager


Explore similar projects

The 965 meter long cable-stayed bridge has won several awards for its advanced engineering. Today, it has become a landmark for Belgrade.

Lilla Lidingöbron is one of Sweden's longest railway bridges. With increased span, the new bridge provides enhanced accessibility and safety, as well as improved frequency for the Lidingö line.

In Värtahamnen, a new quay has been constructed to prepare for a new residential area. The work has been complex as it took place both on land and in water.